Cameroon-Chad Power Interconnection Faces Delay to at Least 2029 Under Current Tender Timelines

The Cameroon-Chad electricity interconnection can no longer meet its December 31, 2027 completion target under the timelines set for major contracts now being tendered, with even the most favorable calculations extending some construction work into 2028 in Chad and 2029 in Cameroon. The African…